Notification: Delay in the Replacement of the Streetlights at Suseong-gwan (Rescheduled for 7/10-7/14)
- 2023-07-05
Notice: Revised Schedule for the Replacement of Streetlights at Suseong-gwan
Please be advised that the replacement work for the streetlights at Suseong-gwan, originally scheduled for this week, has been postponed for one week due to material supply issues.
1. Project Duration: Scheduled from July 10th (Monday) to July 14th (Friday)
- The postponement is necessary due to delays in material supply, resulting in a one-week delay.
2. Scope of Work:
a. Replacement of Emergency Exit Lights: 28 units (medium-sized, LED)
b. Replacement of Pathway Guide Lights: 25 units (small-sized, LED)
c. Installation of Emergency Exit Lights: 2 locations
1 location: Upper part of the corridor fire door near room 61203
1 location: Upper part of the corridor fire door near room 61107
d. Adjustment of Emergency Exit Light Locations:
1 location: Emergency exit light near room 61110 corridor
(Blocked by an exhaust duct)
e. Finishing of the area surrounding the replaced emergency exit lights
f. Related minor construction work
3. Construction Company: MS Fire Protection (Contact: 010-9579-1191)